Residential Renovation · Central London · From £150K

Chaos is Optional

Controlled systems. No surprises.

SIX PAINS

Common renovation failure modes

You said what you wanted. They built what they heard.
The quote was accurate. For a different project.
It was supposed to be 12 weeks. Week 18. No end date.
You emailed on Monday. It's Thursday.
Someone is managing the site. The subcontractors disagree.
The snagging list is longer than the original scope. Getting them back is a second negotiation.

Getting it wrong once is bad luck. Getting it wrong twice is a decision.

The System

Cost Certainty The cost plan locks at pre-construction. Every line item is priced, signed, and frozen before site mobilisation. The final invoice matches the first.
Programme Certainty Thirteen hold points govern every project. Each one carries a written deadline and a named owner. The move-in date is contractual.
Quality Certainty No stage closes until photographic evidence and sign-off confirm the definition of done is met. Defects are caught at the gate, not at handover.
Client Evidence

Pre-construction surveyed the full scope before a contract was signed. The budget risk was found in the document, not on the invoice.The number moved before the hammer did.

"They found the overspend in the survey. By the time we started on site, the contingency already covered it."
Alex · Client · South Kensington
THE WEEKLY RAG

Every Friday at 16:00 you receive the full project state.

Weekly RAG Navigator Section 1 of 6

Five-pillar health check at a glance

The RAG table shows the current status of each project pillar. Green means on track, amber flags a watch item, red demands action.

1 · Project RAG Status
ProgrammeOn TrackFirst-fix progressing to programme. Insulation and plastering complete in WC.
BudgetOn TrackContract sum held. No approved variations. One pending VR under review.
GatesAmber — H5 OpenH5 First-Fix Sign-Off open. Awaiting plumbing pressure test evidence before gate can close.
DecisionsAmber — 1 PendingSanitaryware final selection outstanding. Last responsible moment: 13 Oct 2023.
RisksRed — See S6Exposed pipework in WC void not yet signed off. Risk of programme impact if H5 blocked.

What was done this week and what comes next

A two-column snapshot of completed and upcoming works, plus the programme variance and next gate milestone.

programme
2 · Programme
Completed this week
  • WC — thermal insulation installed between metal studs (non-combustible, 100mm mineral wool)
  • WC — skim plaster coat applied to all walls, scratch coat applied in adjacent space
  • First-fix plumbing terminated: soil pipe, cold supply, UFH manifold connections stubbed through
Next week
  • WC — plumbing pressure test and sign-off (H5 gate evidence)
  • WC — floor screed prep and waterproofing membrane (tanking) prior to tiling
  • Electrical first-fix: confirm light point and ring main positions, run final cable routes
Next Gate
H6 — Second Fix Ready · est. 27 Oct 2023
Programme Variance
On Track — 0 days

Contract sum, variations and forecast

The budget grid summarises the financial position: original contract sum, approved and pending variations, and the forecast final account.

financial
3 · Budget
Contract Sum
£180,000
Approved Variations
£0
Pending Variations
VR-001 — £1,200 (additional noggins for sanitaryware fixing — awaiting approval)
Forecast Final Account
£181,200 (if VR-001 approved)

Gate status and payment milestones

Each construction gate represents a quality checkpoint. The table shows which gates are closed, open, or pending, plus payment status.

governance
4 · Gate Status
GateNameStatusDate
H1–H3 closed on schedule (mobilisation through structural sign-off)
H4First-Fix Services Rough-InClosed22 Sep 2023
H5First-Fix Sign-OffOpen06 Oct 2023
H6Second Fix ReadyPendingest. 27 Oct
Payments: Gate 4 payment (£36,000) invoiced 25 Sep — due 09 Oct. No overdue invoices.

Outstanding decisions and top project risks

Decisions that need client action and the three highest-rated risks this week, with mitigation plans and the governance communications summary.

actions
5 · Decisions Required
DecisionDeadlineImpact if Late
Sanitaryware final selection (WC suite, basin, brassware)13 Oct 2023Delays tiling layout & waterproofing — H6 gate at risk

governance
6 · Top Risks
RiskRAGMitigation
Exposed pipework in WC void — no sign-off evidenceRedPressure test booked w/c 09 Oct. If fail, re-route required — 5-day impact.
Sanitaryware selection delay — tiling holdAmberClient notified of last responsible moment. Provisional layout prepared for early start.
Electrical cable route clash with UFH manifoldAmberRe-route confirmed on drawing. No programme impact if executed next week.
Overdue decisions: 0
Escalations this week: 0
Decisions closed: 2
Pack issued: Fri 06 Oct 2023, 16:00

This week on site

Timestamped site photography documenting progress. Images are blurred for client confidentiality in this sample.

Mineral wool insulation — metal stud wall
Mineral wool insulation — metal stud wall
WC · Insulation
Skim plaster complete — pipework visible at low level
Skim plaster complete — pipework visible at low level
WC · Plastering
Skim plaster — opposite wall with first-fix valve
Skim plaster — opposite wall with first-fix valve
WC · Plastering
Photo pending
Plumbing pressure test
WC · Plumbing
Photo pending
UFH manifold connections
WC · Mechanical
Photo pending
Electrical first-fix cable routes
WC · Electrical

Every Friday at 16:00 you receive the full project state.

Every contractor will tell you they're different. Most of them are right. The question is different how.

Pre-Construction

Before we price anything, we spend four weeks checking the design, the buildability, and the real budget. That's the PCSA. It's a paid engagement. The cost is the point — both sides are serious.

MYX-PB-2025-001 · PCSA IFR — Issued for Review
Pre-Construction Services Agreement
MYX-PB-2025-001 · Rev R01
financial
Financial
Cost plan, exclusions, payment gates
programme
Programme
Timeline, hold points H1–H13, decision deadlines
scope
Scope
What is included, excluded, and who owns interfaces
technical
Technical
Services strategy, plant positions, survey findings
governance
Governance
Variation control, compliance, quality gates
actions
Actions
Your required inputs to reach H1 mobilisation
6 zones · 13 hold points Issued for Review

Enough theory Your turn